# Leaving VMware across two active data centers, on existing hardware

- Link: https://www.silviobalduzzi.com/en/projects/leaving-vmware-two-data-centers/
- Published: 2026-10-24T12:26:14+02:00

## Context

The organization ran four VMware vSphere clusters with vSAN storage, stretched across
two data centers: Windows servers, Linux servers and two clusters for Omnissa Horizon
virtual desktops. That meant more than 450 server VMs plus the desktops of over 
a thousand users. Rising VMware licensing costs made a platform change necessary,
with two constraints: no new servers to buy and no service interruptions.

I wrote the design document, from the workshops with the customer’s technical teams
to the final version that guides deployment and migration. The detailed Horizon 
design belongs to Omnissa Professional Services; I designed the platform, the file
services and the integrations between Horizon and Nutanix.

## The challenge

 * **Off-list hardware.** The nodes were vSAN Ready Nodes missing from the Nutanix
   hardware list, with unsupported NICs and cache drives. They needed a dedicated
   qualification and physical work on every node.
 * **No spare nodes.** Each new cluster could only be built from nodes freed up 
   by a VMware cluster, so the order of the work decided capacity, risk and timing.
 * **Zero RPO on two active sites.** The customer asked for synchronous replication
   for every workload, with both data centers in production.
 * **No Internet access.** Upgrades, images and licenses had to get into a closed
   perimeter.
 * **A mixed VM estate.** Roughly one VM in nine ran an unsupported operating system,
   from Windows Server 2003 to RHEL 3, and more than a hundred were on extended 
   support or could not be identified.

## The approach: Eject, Build, Expand

I turned the constraint into a method. Every node goes through the same cycle: evacuate
the workloads, eject it from the VMware cluster, rework the hardware (Intel E810
25 GbE NICs, cache drives removed, dedicated BIOS settings), reimage it with Foundation,
then create or expand an AHV cluster. The customer’s staff does the physical work,
following Nutanix procedures and with Nutanix sign-off.

The sequence starts with two bridge clusters, one per site, carved out of the VDI
nodes after consolidating the desktops on a single cluster. The Windows servers 
move there temporarily; the nodes they free up build the Linux clusters, then the
Windows clusters, then the VDI clusters. In the end every node reaches its final
place, including two small test clusters for application and firmware upgrades.

The wave plan has nine steps. Each one comes with a capacity plan to validate before
moving on, because N+1 headroom is the weakest point during the intermediate phases.

## Key decisions

 * **One cluster per site, never stretched.** Each group has two twin clusters that
   protect each other with Nutanix Disaster Recovery: asynchronous or NearSync replication
   as the baseline, synchronous with a witness where zero RPO is needed.
 * **Four Prism Central instances.** Scale-out, split by servers and desktops and
   by site, paired as availability zones. The Horizon capacity provider depends 
   on Prism Central, so its resilience is a requirement, not an option.
 * **Trade-offs on record.** RF2 instead of RF3 because of capacity limits, and 
   erasure coding on the server containers, are two customer requests. The design
   records them with their impact and the customer’s risk acceptance instead of 
   hiding them.
 * **Active-active desktops.** Pools sized at 100% on each site, with synchronous
   replication only for the master images. Profiles stay on the existing NAS in 
   the first phase and move to Nutanix Files with Smart DR after functional validation.
 * **Microsegmentation instead of NSX.** Flow Network Security isolates desktops
   from each other: each one talks only to the gateway. Policies start in monitor
   mode.
 * **Dark site.** An internal LCM repository, offline images and licenses, Pulse
   turned off, and log collection from a bridge workstation controlled by the customer.
 * **A plan for legacy VMs.** A test on an isolated network and a rollback for every
   VM. As a fallback, a VMware lab cluster with a deadline for each VM; nested Hyper-
   V only as a last resort, with the lack of support accepted in writing.

## Project status

The design was delivered in October 2026 and is the reference for deployment, migration
with Nutanix Move and validation testing. Decommissioning the VMware environment
and the backup policies remain with the customer.